This is a list of sanitary sewer work anticipated between October 23 and 27. The estimated duration of the work is included.
1. Carlisle, 1st Council District, 2 Months (Dig and Replace) (Street Closure)
2. E Short. 1st Council District, 1 Month (Dig and Replace) (Street Closure)
3. Valhalla , 7th Council District, 2 Days (Repairs) (Not in Street)
4. Kastle, 3rd Council District, 1 Day (Repairs) ( Not in Street)
5. Montavesta, 5th Council District, 1 Day (Cured In Place Pipe – CIPP)
6. E. Main, 3rd Council District, 1 Day (Cured In Place Pipe – CIPP)
7. Wickland , 6th Council District, 1 Day (Cured In Place Pipe – CIPP)
8. Sarasota, 6th Council District, 1 Day (Cured In Place Pipe – CIPP)
Long-term public works construction projects can be found on our project information page.